Switchgear Supply Challenges

The supply chain bottleneck for switchgear is a significant issue, exacerbated by disruptions from Covid. Experts are divided on how quickly the situation will improve, with lead times currently stretching to 60-70 weeks compared to the pre-Covid norm of 20 weeks. The industry is focusing on enhancing manufacturing capacity both domestically and in Europe to expedite recovery.